Inclusions List

Ground Floor Area:                245.88m2        includes Garage 47.02m2
First Floor Area:                       97.07m2
TOTAL:                                  342.94m2

Porch:                                          4.34m2
Terrace:                                       17.0m2
BBQ Area:                                  59.0m2
TOTAL:                                    80.34m2

SUBTOTAL:                          423.28m2

 1.      General

1.               Soil/site classification “M” as per LDA record.
2.               MBA/HIA  fixed price contract & progress payments
3.               Reinforced concrete slab/Waffle slab on lower floor & terrace
4.               Ground floor (including internal to garage) face bricks. Use Boral Bricks Horizon Classics Leura. Flush finish – off-white mortar.
5.               First floor – Harditex Board with applied finish (Owner to choose size) – Stria . Colour the south-western walls different colour.
http://scyon.com.au/stria.html
6.               All timber webs floor trusses between levels
7.               2700mm/4400mm high ceiling to Ground floors
8.               2700mm high ceiling to First floors
9.               2700mm high ceiling to garage floor area
10.           Pine wall frames and prefabricated roof trusses (450mm spacing)
11.           Standard Colorbond roofs as per design – Deep Ocean
12.           Garage Door – Colorbond Deep Ocean
13.           Wet seal to wet areas (bathrooms, powder room, kitchen and laundry)
14.           Certified termite protection as per ACT Building Regulations
15.           Structural steel columns and beams as per engineer’s design
16.           5 hard wired smoke detectors in agreed locations
17.           Work to be performed in accordance with Australian Building Code and relevant construction standards in ACT
18.           Comply with the Wright Housing Development Guide, including the Bushfire mitigation measures that apply to Block 7 Section 11 Block 7. BAL-12.5 AS.3959-1999 BUSH FIRE MITIGATION MEASURES.
19.           Site preparations, excavations, and fillings as per plans and construction requirement
20.           Drainage plan and fee
21.           Survey report and fee
22.           Private Certifier’s fee
23.           Building Levy
24.           Training levy 
25.           House cleaned internally and externally and all construction debris removed
26.           Tap and connect all services, including hot and cold water, electricity, stormwater drainage and sewer drainage, according to the regulations of ACTEW. Pay for services used in building work.
27.           Excavate and level to 0.5m of fence lines to neighbours.
28.           Note all Floor tiling needs to including skirting with the same floor tile.
29.           Arrange/provide Certificate of Occupancy on completion
30.           Ease and adjust doors and windows, clean glass, remove paint spots and runs, sweep floor and leave in a clean and habitable condition.
31.           Label all keys and hand to the Owner, together with any certificates and guarantees reasonably required by the Owner.
32.           Reinstate any driveways, grass, shrubs, fences, walls, etc that may receive damage during the construction period.
33.           2x 4000L slimline rain water tank with main pressure control valve, connected to 4 toilets and washing machine and all external taps.
34.           Generally all plumbing go into wall, not directly into floor.
35.           WAKAFLEX non-lead flashing.
36.           Connect to water mains as indicated on the drawings. Run 12mm branches to showers, basins, kitchen sink, laundry tub and washing machine and WC cisterns. Also include outlet with hot/cold mixer to the right of toilet seats. Fix 12mm tested brass high pressure mixers, pillar cocks or recess cocks with breeching piece and spout to all house points unless otherwise scheduled. Keep service pipes clear of building. Secure all pipes on walls with sturdy clips and holdfasts. Conceal piping where possible. Where exposed in rooms, chrome plate all pipes and taps.
37.           Letterbox in left front porch piers.
38.           2 sky lights upstairs, 1 downstairs (standard 600x600 skylights) – owner to decide where.
39.           All carpets - Double underlay depending on carpet thickness.

2.      Electrical Service, Gas, Telephone and Data

40.           Plumbing, drainage, gas, electrical connection (builder responsible for registration of gas and electricity)
41.           Telephone conduit from main to house for later connection by owner. Telephone points in 1 x Family room (telephone cupboard), 1 x Study, 1 x upstairs hallway, 1 x hallway outside Bedroom 2.
42.           Ducted vacuum system with 6 connection points (as long as whole house is covered including one in Garage).
43.           Security alarm with 6 sensors. Motion, door and window sensors throughout the house with back-to-base option.
44.           Valet Intercom system. One S1-MV Master Station. One Alloy video door station, 10 Room stations
45.           8 Gas points – one for Gas fireplace, one for kitchen stove, one in laundry, three in pergola area. One in garage. One in hallway outside Bedroom 2.
46.           HPM Standard Outlets Double Powerpoints 777 x57.
47.           HPM Surge Protected Powerpoints – XL777PA x13 (study, family, lounge, upstairs)
48.           HPM 2WS38 External. Allow for 6.
49.           Provide electrical cable and conduit to allow for lighting at front south to the front east.
50.           HPM or equal wall mounted light switch – brushed chrome finish – 45 light switches
51.           Follow TRANSACT’s guide for builders for Fibre to Home: http://www.transact.com.au/documents/home_preparation_guideline.pdf.
52.           Cat five cabling with 5 data points to a Gigabyte Ethernet router (owner to provide) in telephone cupboard. Data points in Study room (2), lounge, family room, upstairs hallway.
53.           3 phase circuit board with earth leakage protection. Zone in metre box to allow for shutting down parts of the house without impact to critical points. To consult with Owner.
54.           Put metre and transact boards on western (left side) wall outside garage.
55.           Consider separate metres for bedroom 1 and 2 area. Also separate gas, separate transact?

                                          

3.      Heating and Cooling, Hot Water

56.           Ducted gas heating (2 units) and electricity cooling system(2 units) from 2 controllers with time and 2 zones for upper and 2 zones for ground levels. Ensure cooling system achieves a achieves a minimum of 2.9 stars, in accordance with the Minimum Energy Performance Standard (MEPS) Scheme. Entry, Prayer Area, Lounge, Dinning, Kitchen, Family, Study, Bedroom 1, 2 Bathroom 1, 2 Upstairs – Bed 3, 4, 5, 6, Bathroom 3 and Hallway.  Zone Bedroom 1& 2 and hallway and Bathroom 2 separately with control in hallway near Bedroom 1.
57.           Full ground floor in-slab heating for all of downstairs and upstairs bathroom(separate zone) using 12 circuit manifold allowing for separate controls of areas with 24 hour electronic thermostat with gas fired boiler (30KW). Use 16 mm Raupink Pex A cross linked polyethylene AS 2492 DIN 4726 floor heating pipe. Ensure all necessary work for concrete slab takes this into account including perimeter and slab. Also Include reinforcing mesh, twin active wire from thermostat to boiler and all gas, water, electrical and powerpoint connection to boiler. Solar powered with gas backup including supply and installation of 2 x 30 evacuated tube solar panels. Integrate with the solar hot water with this system. Specifications as per Appendix B.
58.           Solar hot water: The RECS for the Solar Hot Water System as above must meet the requirements of the Water and Sewerage Regulation 2001 (ACT) based on the number bedrooms and Zone 3. The solar water heater must be installed in accordance with the requirements of Section 5.4.3 of the Housing Development Guide. The Housing Development Guide is located at:  http://wright.molonglovalley.com.au/design/housingguides/
59.           2 x 26L Rinnai infinity hot water unit each with 2 controls (1 per unit) flush into the wall.


4.      Insurance, Maintenance & Guarantee

60.           Maintenance period 90 days
61.           6 years Housing Indemnity Insurance Warranty
62.           10 years Construction Warranty 
63.           Comply with the Worker's Compensation Ordinance, and
64.           Provide for all circumstances whereby the Owner may be liable under Common Law or Statute for any act or omission of the builder.
65.           Insure the Owner against Common Law Liability - amount to be unlimited.
66.           Insure the Owner against Public Liability, amount to be not less than $2,000,000.00.
67.           Insure the works against fire, or loss, or damage from any cause whatsoever. Insure for the full value of the works plus 10% for professional fees, approvals and removal of debris.
68.           The Contractor shall obtain, and ensure that the Owner will have the benefit of, warranties or guarantees as specified in the Contract, including warranties or guarantees that are obtained by the sub-contractors of the Contractor.


5.      External Finishes

69.           Standard colour range aluminium windows deep ocean (colour to be discussed) and slider doors all double glazed (3mm glass with 6mm gap), all with keyed-alike locks and standard fly screens to windows (standard high window 2.50m including fly screen. Builders range from Trend Windows or Dowell Windows) - Must be in accordance with energy rating regulation 2010.
70.           Fix 0.56mm colorbond gutter of bullnosed quadrant section type with beaded edge. Install colorbond steel fascia/bargeboard equal to Stramit Fascia and Stramit 125 Guttering.
71.           In addition, spouts are required in guttering to control overspill in heavy rainfall. Lap in direction of flow, fix to manufacturer's instructions with double rivet and silicone seal all joints. Provide thimble connections to downpipes. Fix in longest lengths possible supported at 900mm centres with 30mm x 1.6mm zincalume brackets well-spiked to fascias or framing and folded around beaded edge. Install leaf guard equal to All Clear Leaf Guard along all guttering.
72.           All External and Garage doors to be keyed alike. Eastern external door – separate key.
73.           All sliding external doors to be keyed alike.
74.           Crimsafe or similar Security dead-lockable triple-lock screen doors for sliding doors in family room and to upstairs terrace.
75.           Colorbond metal fascia, gutter & downpipes to be painted to match wall colour
76.           Swing folding clothes line (largest) and concrete path  
77.           Plain concrete driveway with L&D Conditions (SL82 mesh). Concrete to front of porch, allowing car to turn inside property.
78.           Plain concrete paths (SL62 mesh) around house as per plan, minimum 1m wide –both reinforced concrete minimum100mm thick
79.           Plain concrete driveway with L&D Conditions (SL82 mesh) on east side of house and underneath Pergola – sufficient for car parking.
80.           Weather seal to all external and garage swing doors
81.           1.8 m high Colorbond fence with 2 Colorbond gates (single gate on one side of the house and the other side a double gate 2.4m opening and 1.8m height) –
82.           1.8m high Colorbond fences along west and north borders. Owner to arrange 50% funding from neighbours.
83.           5 external double taps – allow for piping under concrete footpaths and driveways for hose to garden areas.
84.           Fire gutter protection – All Clear Leafguard.
85.           Concrete upstairs terrace area.
86.           Pergola area with concrete and with 150x50 aluminium beams / 100x100 posts
87.           Roofing for Pergola - Laserlite 2000+ Clear first 3m in front of family and study  and Laserlite 3000 Ice in the remainder.

6.      Internal Finishes

88.           2700mm ground and 2700mm first floor ceiling height
89.           10mm thick plasterboard to walls
90.           10mm thick plasterboard to ceilings
91.           90mmx45mm thick internal timber frame partition walls with 450mm span – Australian Standard is 90x45 is external for load bearing walls with two support knogginas, and internal walls are 90x45 with two support knoggings for gybrock/willaboard
92.           Square set cornice to lower floor and first floor with metal profil
93.           Villa board to wet areas – bathrooms, ensuite, laundry and mud space.
94.           MDF internal door frames, architraves - 68mm, skirtings - 90mm  to be painted with acrylic paint
95.           Paint one coat Dulux Oil Based Undercoat and tow coats Dulux Super Enamel Semi Glass.
96.           Paint 1 coat Dulux Trade Timberlook Interior Stain and two coats Dulux Clear High Gloss Polyurethane.
97.           Hume citizen door (solid timber flat door SC Readicote (9314916391291) standard high 2050mm door).
98.           Gainsborough quality door furniture & robe knobs allowance $40 each (FAW or Magnet Mart or Bunnings)
99.           Door stops to all swing doors (75mm Projection wall stop, zinc,CP)
100.       Full Mirrored Shaving Cabinets to suit vanities.
101.       All robes and linen shelves in melamine (standard builders range from Dolphin or VSL Joinery)
102.       General hallway lights: Beacon Lighting Envirolux Saturn.
Saturn Round Flush Mount in Brushed Aluminium/Opal
103.       All internal sliding cavity doors to have Gainsborough Circular Sliding Cavity Door Privacy Lock Bright Chrome or similar.
104.       All internal normal doors to have Gainsborough G2 Series Contemporary Precise Privacy Lever Bright Chrome or similar.

7.      Insulation

105.       Fibreglass batts R 5.0 and sisalation to ceilings and floor between upper and ground levels
106.       Fibreglass batts R 2.5 and sisalation to walls between garage, laundry, mud space and pantry areas.
107.       Insulation to internal walls – study to bathroom as per plan sound proof R4.0
108.       Aluminium foil (sarking) under roof tiles and external wall
109.       Insulation as per plan requirements


Lower floor

8.      Garage

110.       1 Panelift standard door (opening 4.8m & height of door 2.15m and small door on back side opening 2.4m and height 2.15m) with 3 remote controls
111.       1 single power point for garage opener
112.       3 double power points including 1 powerpoint for vacuum system (2+1).
113.       3 florescent lights  (3 switches)
114.       External flood light to front of garage (builders range – JP) with sensor lights
115.       1 x TARIFA 2LT E27 RECT PLAIN BUNKER SILVER exterior light at back of Garage
116.       Cupboards under stairs accessible from Garage – consider placement for boiler or vacuum. – to discuss.

9.      Porch

117.       2 down lights  - to discuss
118.       Outside of porch 1 x down light  - to discuss
119.       1 Light - Envirolux Dawn T5 2x28w S/M Wh 42k – Flourescent
120.       2 x Sentinel 2 Light Wall Bracket In Stainless Steel. One on each pillar.
121.       Colour video intercom connected to family & upstairs in hallway.
122.       External two front pillers – Austral Lite Stone Calcite blend
123.       Timber benches for seating on either side of entry porch to client requirements (consider Ceasarstone benches).
124.       External tiling same as Terrace
125.       External flood light to front (builders range – JP) with sensor lights
126.       Grade the entry so that it slopes up towards the doorway allowing for a smooth transition to the tiled internal entrance without timber in doorway.

 

10.  Entry & Downstairs

127.       Crown 12v 12lt 58cm flush chr/crystal chandelier
128.       2 wall lights SEKA WSCONCE –SAT/OPAL single globe
129.       2 double power points
130.       Gainsborough Trilock Contemporary G2  Series Precise Lever Set Bright Chrome (allowance $200)
131.       3 recessed features in walls as per plan
132.       Sliding door to living area as per plan
133.       Front door – Hume Doors and timber Newington Range XN6 Double Doors with Wave safety glass – height of 2400mm
134.       Windows on each side able to be opened slightly for parcels.
135.       Entry double door with allowance $500 each
136.       Gainsborough Storm Door Seal
137.       Super White Porcelain Tiles 600mm x 600mm
138.       Heating in the slab downstairs. (Zone 1)

 

11.  Living (Lounge)/Prayer

139.       5 double power points
140.       1 data port
141.       4 Theatre 2lt W/S Matt Opal 2 Globe Wall Light
142.       3 ceiling fans Typhoon 56 with lights
143.       1 TV antenna point
144.       2 Light dimmer switches (1 for prayer, 1 for lounge)
145.       Coonara Grange Classic Inbuilt Stainless Fire Place
146.       Cavalier Bremworth Plush Pile 100% Pure New Wool Pebbledash earthy grey (Living)
147.       Cavalier Bremworth Plush Pile 100% Pure New Wool Pebbledash earthy grey (Prayer)
148.       1 Room Station intercom
149.       Heating in the slab (Zone 3)

12.  Dining

150.       3 double power points
151.       5 down lights (to discuss)
152.       Crown 12v 12lt 58cm flush chr/crystal chandelier
153.       2 wall lights SEKA WSCONCE –SAT/OPAL single globe
154.       1 Light dimmer switch
155.       Super White BT3007 Porcelain Tiles 600mm x 600mm
156.       Heating in the slab (Zone 3)


13.  Family

157.       8 double power points
158.       4 Theatre 2lt W/S Matt Opal 2 Globe Wall Light
159.       1 phone point
160.       1 data point
161.       1 Light dimmer switch
162.       1 TV antenna point
163.       1 Valet S1-MV Master Station intercom set connected to porch
164.       Super White Porcelain Tiles 600mm x 600mm
165.       Heating in the slab (Zone 1)


14.  Staircase

166.       Maple timber stair case (standard builders range from Beachhouse stairs)
167.       Maple timber handrail to walls (standard builders range from Beachhouse stairs)
168.       Plaster board wall between stair
169.       5 wall stair lights with 2 way switches to discuss
170.       3 double powerpoints
171.       Under stair access as per plan plasterboard finish
172.       Timber matching upstairs hallway.

15.  Kitchen

173.       6 double power points (including two on Island)
174.       8 down lights with dimmer switch
175.       Envirolux Linea 14w T5 U/Shelf Wh 42k (to discuss)
176.       1 Envirolux Saturn 32w T5 Fluro Br Ch movement sensor light  to WIP
177.       1 double power point to WIP
178.       1 single power point to microwave
179.       1 single power point to refrigerator
180.       1 single power point to rangehood
181.       1 single power point to cooktop
182.       1 single power point to dishwasher
183.       Provision for Dishwasher tap & power
184.       Electric oven  (BOSCH HBA 13B 150A-A 60cm 4 Function Electric Clock Oven)
185.       Electrolux 90cm Gas Cooktop EHGC95AS9315538442798 http://www.harveynorman.com.au/electrolux-cm-gas-cooktop.html.
186.       Range hood (DELONGHI DESIGMA90  - 90cm 3 Speed electric touch ctrl canopy St/Stl)  
187.       Rangehood duct to outside
188.       Additional exhaust fan 300mm ducted to outside. Hellar Ii 250mm Exh Fan White
189.       Stove splashback: Stainless steel
190.       Kitchen splashback: Decoglaze toughened splash back – lake tide.
191.       Dishwasher (BOSCH SMU50E05AU –A – 60cm Built Under Dishwasher 3.5star WELS 2star Energy) – white front
192.       Wrap Around Laminex Doors White Flush Panel
193.       Water outlet behind Fridge for connection to fridge.
194.       Sink – (CLARK 30071) – Benchmark 1538mm Dbl Ctr Bowl Sink 1TH. Sink is set within Ceaserstone bench.
195.       Ivy Sink Mixer CP (5S) – (PHOENIX YV730CHR-A)
196.       Square set bulk head as per plan
197.       Drawers throughout under the benches.
198.       Island. Double Sink, Breakfast preparation on north with cupboards underneath with sliding doors. Between sink and prep area will be a 30cm high ceaserstone or glass splashback with 300mm deep shelf top. The prep area will have a four-point powerpoint 5cm below the shelf.
199.       Kitchen with sink in wrapped gloss kitchen and Caesar stone bench tops (Essastone Bench Top Crystal Chalk or similar) 40mm (builder’s allowance $18,000) – Included Pantry area and telephone cupboard next to kitchen is a part of the kitchen pantry with internal sensor light.
200.       Super White BT3007 Porcelain Tiles 300mm x 300mm
201.       Heating in the slab (Zone 1)


16.  Laundry & Mud Space

202.       2 x  Envirolux Saturn 32w T5 Fluro Br Ch – 2 light switches
203.       3 double power points
204.       1 external down light – 2 way switch
205.       65L Stainless steel drop in tub with flick mixer – as we previously discussed this needs to be standard 65L S/S tub as your bench space is 600mm wide. If it’s 65L then bench space needs to be increased to 800mm and the tub is a special order item attracting extra charge.
206.       Ivy Sink Mixer CP (5S) – (PHOENIX YV730CHR-A)
207.       Hot & Cold tap taps for washing machine connection
208.       2 x External door – Solid timber door with Gainsborough Trilock Contemporary G2  Series Precise Lever Set Bright Chrome plus Ryobi 1500 Series Fire Rated Door Self-Closer and Lockwood 530 Digital DX Entrance Set On each
209.       Laundry chute from first floor.
210.       Mud Space – Owner to take responsibility.
211.       Super White BT3007 Porcelain Tiles 300m x 300m ($35.00/m2)
212.       A “wavy” white wall tile floor to ceiling. For example Toledo Blanco Wavy 300 x 600
213.       Solid timber sliding door (height 2050, opening 820 - Product No. 931491691291 SC Readicote from FAW).
214.       Heating in the Slab (Zone 1)


17.  Bathroom 1

215.       2 x ENVIROLUX SATURN 22W T5 FLURO BR CH lights – with dimmers
216.       1 x HELLAR II 250MM EXH FAN WHITE (200246) 1 switch for one light (in bathroom) and fan
217.       2 double powerpoint – one at each sink
218.       Mirrored Shaving Cabinet to suit vanity
219.       Spa Bath (SERVICE MISCELLANEOUS-P) – Caroma VT7WF Vitality 1675mm Bath w/Steel Frame. 1 step into spa with grab rail
220.       Bench making it easy to sit and wash feet in spa
221.       Swivel Spout as in above, position in middle of bath under window with mixer on the side where person will lie
222.       Built on top of spa, glass shower screen. Regency framed shower screen frosted doors. Full sliding bath enclosure matt silver x1 – 3 door slider above bathtub that when fully extended, it covers half the bathtub from west wall to allow showering without getting floor wet. Plus shower rail for curtain for the remainder of the length of the tub.
223.       Bathroom tiles floor to ceiling (wall tiles wavy 300 x 600)
224.       Bathroom feature wall strip (border)
225.       Super White BT3007 Porcelain Tiles 300m x 300m
226.       Cavity Slider Door is extra size 1020mm opening to 2050mm height – solid timber door.
227.       Flick Mixer (PHOENIX YV770CHR-A) – Ivy Basin Mixer – Swivel CP (4S)
228.       Vanity 1 ( LAVITA VSE 1900SKLH) – Sevilla 900mm S/Rec Vanity 2Drs 3LH.  Consider Caesar stone bench tops (Essastone Bench Top Crystal Chalk or equivalent) with dropin sink.
229.       Vanity 2 (next to bathtub) (LAVITA VSE11200SK) – Sevilla 1200mm S/Rec vanity 2Cts Drs 6 Drws 1 TH
230.       1 x Double Cosmo Metal Towel Rail 900m
231.       2 x Cosmo Metal Towel Ring CP
232.       Mirror 1100 x 800cm shaving cabinets
233.       Heating in the slab (Zone 1)
234.       Bathroom benchtop: Caesar stone bench tops (Essastone Bench Top Crystal Chalk or equivalent)

18.  WC

235.       1 x ENVIROLUX SATURN 22W T5 FLURO BR CH lights
236.       1 x HELLAR II 200MM EXH FAN WHITE (200245) 1 switch for light and fan
237.       Small wall basin (ARGENT FC 110MUL01) with flick mixer & Shaving Cabinet (600x800mm) on top (size of vanity)
238.       Small Cabinet under basin (ARGENT ED10SW0401 W/Hung Cabinet)
239.       Mixer  as in Appendix C connected to “spout” with thread to the right of toilet where hose can be screwed on.
240.       Toilet (CAROMA 904600W) – Metro Uni Trap Btm/I Toilet Suite WH
241.       Toilet Roll Holder (CAROMATAPS 305001C) – Cosmo metal toilet brush & holder CP
242.       1 x Cosmo Metal Towel Ring CP
243.       Bathroom tiles floor to ceiling (wall tiles wavy 300 x 600)
244.       Bathroom feature wall strip
245.       Super White BT3007 Porcelain Tiles 300m x 300m
246.       Sliding Cavity Solid timber door (height 2050, opening 720 - Product No. 931491691291 SC Readicote from FAW).

19.  Bathroom 2 (Between Bed 1 & Bed 2)

247.       2 x double powerpoint (one near sink, one in shower changing area),
248.       See Appendix C for shower and fittings.
249.       Regency Framed Shower Screen Doors. 3 Door Slider Front with Opening near door
250.       1 extendable round double-sided shaving mirror
251.       Toilet (CAROMA 904600W) – Metro Uni Trap Btm/I Toilet Suite WH
252.       Toilet Roll Holder (CAROMATAPS 305001C) – Cosmo metal toilet brush & holder CP
253.       3 x ENVIROLUX SATURN 22W T5 FLURO BR CH lights
254.       1 x HELLAR II 200MM EXH FAN WHITE (200245) – connected to light switch
255.       2 x HELLAR II 250MM EXH FAN WHITE (200246) – connected to light switch
256.       Small wall basin (ARGENT FC 110MUL01) with flick mixer & Shaving Cabinet (600x800mm) on top (size of vanity)
257.       Small Cabinet under basin
258.       Mixer  as in Appendix C connected to “spout” with thread to the right of toilet where hose can be screwed on.
259.       Vanity 1 ( LAVITA VSE 1900SKLH) – Sevilla 900mm S/Rec Vanity 2Drs 3LH
260.       Flick Mixer (PHOENIX YV770CHR-A) – Ivy Basin Mixer – Swivel CP (4S)
261.       Bathroom tiles floor to ceiling (wall tiles wavy 300 x 600) – border with different colour.
262.       Super White BT3007 Porcelain floor Tiles 300m x 300m
263.       2 x Solid sliding cavity timber door (height 2050, opening 820 - SC Readicote from FAW).
264.       Shower Rail (MEHVEN 132201) – Genesis SJ 2F Shower on Rail CP (3S)
265.       Heating in the slab



20.  Study Room

266.       Super White BT3007 Porcelain Tiles 600m x 600m
267.       3 x ENVIROLUX SATURN 22W T5 FLURO BR CH lights
268.       8 x double power points with surge protection
269.       Heating in the slab (Zone 1)
270.       2 x Solid sliding cavity timber door (height 2050, opening 820 - SC Readicote from FAW).


21.  Bedroom 1

271.       Solid timber door (height 2050, opening 820 - Product No. 931491691291 SC Readicote from FAW).
272.       3 x down lights to discuss
273.       Typhoon 52in Fan Only White With Light
274.       2 x Wall Lights Seka W/Sconce-Sat/Opal
275.       4 double power points
276.       2 dimmer switches above the bed head
277.       1 TV antenna point
278.       1 phone point
279.       Built in robe with 1 bank of shelves, 1 top shelf, 25mm chrome hanging rail (Robe and shelving in laminate with sliding doors - full mirror doors) - {Builders range from Dolphin or VSL}
280.       Cavalier Bremworth Hardtwist Cut Pile 100% Pure New Wool Picotage Colour to be determined (colour to be confirmed)
281.       Outside bedroom in hall Envirolux Saturn 32w T5 Fluro Br Ch
282.       Solid timber door (height 2050, opening 820 - Product No. 931491691291 SC Readicote from FAW).
283.       Heating in the slab Zone 2


22.  Bedroom 2

284.       3 x down lights
285.       Typhoon 52in Fan Only White With Light
286.       2 x Wall Lights Seka W/Sconce-Sat/Opal
287.       4 double power points
288.       Built in robe with 1 bank of shelves, 1 top shelf, 25mm chrome hanging rail (Robe and shelving in laminate with sliding doors - two mirror doors) - {Builders range from Dolphin or VSL}
289.       Cavalier Bremworth Hardtwist Cut Pile 100% Pure New Wool Picotage Colour to be determined
290.       Outside bedroom in hall Envirolux Saturn 32w T5 Fluro Br Ch
291.       Solid timber door (height 2050, opening 820 - Product No. 931491691291 SC Readicote from FAW).
292.       Heating in the slab Zone 2

23.  Hallway (Between Bed 1 & Bathroom)

293.       3 down lights with 2 way switchers – to discuss
294.       Envirolux Saturn 32w T5 Fluro Br Ch with 2-way switchers
295.       Hot/Cold water service for future use
296.       Water and Drainage Waste
297.       Gas service for future use
298.       Phone line
299.       Data point
300.       2 x Solid sliding cavity timber door (height 2050, opening 820 - SC Readicote from FAW).
301.       Heating in the slab Zone 2

24.  Side External Entry and Porch

302.       1 down lights (to discuss)
303.       6  x Tarifa 2lt E27 Rect Plain Bunker Silver Exterior Lights on south and east sides of house
304.       Newington Single Door with Gainsborough Trilock Contemporary G2  Series Precise Lever Set Bright Chrome
305.       Gainsborough Storm Door Seal

25.  BBQ/Pergola Area

306.       6  external down lights (to discuss)
307.       6  x Tarifa 2lt E27 Rect Plain Bunker Silver Exterior Lights – 3 switches
308.       3 x Envirolux Dawn T5 2x28w S/M Wh 42k
309.       1 x Typhoon 56 Fan lights
310.       4 Gas points
311.       4 x external powerpoints waterproof
312.       1 Hold/cold water plumbing for future use
313.       80L laundry tub

26.  Under Terrace Area including Left side Pergola Area

314.       2 x Envirolux Dawn T5 2x28w S/M Wh 42k

27.  Garage Side near water tank

315.       2 x flood light  Twin Flood Sensor Boxed Black Outdoor Security

Upper floor

28.  Bedroom 3

316. Solid timber door (height 2050, opening 820 – Product No. 931491691291 SC Readicote from FAW).
317. Typhoon 52in Fan Only White With Light
318. 2 x Wall Lights Seka W/Sconce-Sat/Opal
319.       4 double power points
320.       Built in robe with 1 bank of shelves, 1 top shelf, 25mm chrome hanging rail (Robe and shelving in laminate with sliding doors - mirror doors) - {Builders range from Dolphin or VSL Joinery}
321.       Cavalier Bremworth Hardtwist Cut Pile 100% Pure New Wool Picotage Silver Cloud (colour to be confirmed)

29.  Bedroom 4

322.       Solid timber door (height 2050, opening 820 - Product No. 931491691291 SC Readicote from FAW).).
323. Typhoon 52in Fan Only White With Light
324. 2 x Wall Lights Seka W/Sconce-Sat/Opal
325.       4 double power points
326.       Built in robe with 1 bank of shelves, 1 top shelf, 25mm chrome hanging rail (Robe and shelving in laminate with sliding doors - mirror doors) - {Builders range from Dolphin or VSL Joinery}
327.       CAVALIER BREMWORTH HARDTWIST CUT PILE 100% PURE NEW WOOL PICOTAGE COLOUR TO BE DETERMINED

30.  Bedroom 5

328.       Solid timber door (height 2050, opening 820 - Product No. 931491691291 SC Readicote from FAW).
329. Typhoon 52in Fan Only White With Light
330. 2 x Wall Lights Seka W/Sconce-Sat/Opal
331.       4 double power points
332.       Built in robe with 1 bank of shelves, 1 top shelf, 25mm chrome hanging rail (Robe and shelving in laminate with sliding doors - mirror doors) - {Builders range from Dolphin or VSL Joinery}
333.       Cavalier Bremworth Hardtwist Cut Pile 100% Pure New Wool Picotage Colour to be determined

31.  Bedroom 6

334.       Solid timber door (height 2050, opening 820 - Product No. 931491691291 SC Readicote from FAW).
335. Typhoon 52in Fan Only White With Light
336. 2 x Wall Lights Seka W/Sconce-Sat/Opal
337.       4 double power points
338.       Built in robe with 1 bank of shelves, 1 top shelf, 25mm chrome hanging rail (Robe and shelving in laminate with sliding doors - mirror doors) - {Builders range from Dolphin or VSL Joinery}
339.       Cavalier Bremworth Hardtwist Cut Pile 100% Pure New Wool Picotage Colour to be determined

32.  Hallway - Upstairs

340.       Boral 19mm Solid Strip Timber Flooring – Flooded (Rose) Gum – align level with bathroom floor.
341.       Void wall Height 1100mm cover with plaster finish
342.       2 x Envirolux Saturn 32w T5 Fluro Br Ch lights
343.       2 x wall lights Seka W/Sconce-Sat/Opal Single
344.       Upstairs cupboard double doors – Hume Lincoln XL8.


33.  Upstairs Terrace

345.       Concrete floor 
346.       Balustrade & Frieze: Powdercoat aluminium colorbond deep ocean, glass
347.       2 x Envirolux Saturn 32w T5 Fluro Br Ch lights
348. 1 gas point
349. 1 hot/cold water for future use
350. Water and drainage waste
351. 1 external double powerpoint waterproof
352. External floor tiles (non-slip) same as porch

34.  Bathroom 3 (Upstairs)

353.       4 X Envirolux Saturn 22w T5 Fluro Br Ch Lights – To Discuss
354.       2 X Hellar Ii 250mm Exh Fan White (200246) – To Discuss
355.       2 x Solid sliding cavity timber door (height 2050, opening 820 - SC Readicote from FAW).
356.       3 x  - Vanity ( LAVITA VSE 1900SKLH) – Sevilla 900mm S/Rec Vanity 2Drs 3LH
357.       4 double powerpoints
358.       1 x 4 rows Heated towel rails
359.       3 x Flick Mixer (PHOENIX YV770CHR-A) – Ivy Basin Mixer – Swivel CP (4S)
360.       3 x Single Cosmo Metal Towel Rail 900m
361.       On top of each vanity (left & right) is a mirrored Shaving Cabinet to fit vanity.
362.       Bathroom tiles floor to ceiling.
363.       Super White BT3007 Porcelain Tiles 300m x 300m
364.       2 x  Toilet (CAROMA 904600W) – Metro Uni Trap Btm/I Toilet Suite WH
365.       2 x Toilet Roll Holder (CAROMATAPS 305001C) – Cosmo metal toilet brush & holder CP
366.       Mixer  as in Appendix C connected to “spout” with thread to the right of toilet where hose can be screwed on.
367.       Regency Framed Shower Screen Doors. 3 Door Slider Front with Opening near door
368.       2 extendable round double-sided shaving mirror near vanities
369.       Shower Rail (MEHVEN 132201) – Genesis SJ 2F Shower on Rail CP (3S)
370.       Shower Flick Mixer (PHOENIX YV770CHR-A) – Ivy Basin Mixer – Swivel CP (4S)
371.       Shower Head Save Water
372.       Heating in the slab Zone 4